The first box girder of cast bridge of Chengdu Fifth Ring Road Project of China Power Construction Road and bridge group was successfully

Long press the QR code to pay attention to the wonderful recommendation.

The first precast bridge of Chengdu Fifth Ring Road Project of China Power Construction Road and bridge group Smooth installation of precast pier columns and the first cap beam of cast bridge of Chengdu Fifth Ring Road Project of China Power Construction Road and bridge group; smooth installation of pier columns and cap beam phase I hoisting nodes of Qingbaijiang section a of Chengdu Fifth Ring Road of China Power Construction Road and bridge group; perfect ending of Luzhong construction’s enterprise spirit: realism, innovation, progress and high efficiency; Luzhong construction’s service philosophy: professionalism, focus, dedication and concentration, Let users rest assured.

Quality first and refinement oriented.

Review of construction progress 2021.08.23: our company successfully completed the installation of the first Precast Pier Column 2021.11.10: our company successfully completed the installation of the first bent cap 2022.01.05: our company successfully completed the installation of all Precast Pier Columns and bent caps of phase I project of section a 2022.02.22: our company successfully completed the installation of the first precast box girder of the Fifth Ring Road project.

The 16.09m domestic largest diameter shield machine Cutterhead of “juli-1” of Jiangyin Jingjiang Yangtze River Tunnel of CCCC Shanghai Luzhong Construction Machinery Co., Ltd.

In 2022, Luzhong construction’s new employee induction training and dismantling crawler crane safety training meeting was held to cheer up the strength of the tiger in the year of the tiger and rejuvenate the spring! Pay tribute to Lu Chongren who sticks to his post during the Spring Festival! Luzhong construction work report in late January 2022 Luzhong construction work report in mid January 2022 Luzhong construction work report in early January 2022 picture provided by: Zhang Kaining article reviewed by: Wang Hua copyeditor: Liu Gong..

User first, service-oriented.

Introduction to the successful installation of the first precast small box girder of Chengdu Fifth Ring Road Project [construction unit] China Power Construction Road and Bridge Group Co., Ltd.

was successfully lowered into the well.

We patiently overcome every difficulty and successfully completed the construction plan for the installation of eight box girders on the first day of box girder installation.

The construction of bridge pier column, bent cap and box girder is cast, and the construction technology requirements are high.

Bend Loop

[construction project] phase I project of Qingbaijiang section a of Fifth Ring Road [operation content] installation of precast pier column, cap beam and box girder Chengdu Fifth Ring Road is located between the ring expressway and the second ring expressway, All the municipal districts in the second circle of Chengdu are connected in series, and the whole line adopts the technical standard of class I highway.

Luzhong construction will always promise: reputation first and honesty oriented.

Qingbaijiang section (viaduct in the whole process) is the first section of the Fifth Ring Road.

[professional subcontractor] Luzhong Construction Engineering Co., Ltd.

It is a super large bridge with a total length of 850 meters and a bridge beam width of 28 meters.

Luzhong construction specializes in shield machine transportation, hoisting, installation, disassembly, maintenance, municipal bridge erection, precast bridge installation and other businesses, and wholeheartedly provides high-quality services for our customers.

Safety first and people-oriented.

In order to hoist smoothly, our company adopts a 350t truck crane and a 400t truck crane for cooperative operation.

Due to the small impact of the construction site, the transfer of truck crane has brought certain difficulties to the construction.

Hoisting and installation of box girder the whole box girder is about 30m long, and the heaviest side beam weighs about 110t.