Is the overall stability and structural durability of the fully assembled high pile wharf really good?

Including 1 approach bridge, 1 wharf platform, 1 fire control platform, 1 oil and gas recovery platform, 2 mooring piers, 2 temporary steel bridges and relevant auxiliary facilities.

The construction period of the contract is only 6 months, which is half shorter than that of the traditional wharf construction in the past.

The total number of precast components of the wharf after “assembly” is reduced from thousands to 195, which greatly saves the manufacturing and installation time of precast components and increases the assembly rate of the project from 30% to more than 70%.

The main body of the wharf of the project was completed on November 24, 2021, which was 24 days ahead of the contract period.

At the initial stage of project construction, the project team paid close attention to scientific and technological innovation and adopted a new type of fully assembled structure for the first time to overcome many difficulties, such as tight construction period, large technical difficulties, short offshore construction window, etc.

It is a high pile beam slab structure.

The key parts are cast-in-place, which is reassuring…

In addition, according to the information from CCCC third Harbor Bureau, the six harbor basin 64\65\65\liquid bulk cargo berth project in Xuwei port area of Lianyungang port was undertaken by the Shenghong Wharf Project Department of the third Harbor Bureau.

The berth has a total length of 648m and a width of 25m.

organized and held the handover Acceptance Meeting for the hydraulic building (structure) works of the liugangchi 64\65\liquid bulk cargo berth project in Xuwei port area of Lianyungang port.

This structure enables the main structure of the wharf to be “spliced” into a super large precast beam from the traditional three pile caps, and the superstructure of the wharf is “spliced” into a special-shaped beam slab – π type precast beam slab from the original precast longitudinal beam, longitudinal and transverse beam cast-in-place joints and precast panels.

The pile cap casts the high pile, cross beam and longitudinal beam together, so that the whole structure is stressed to form a rigid body, which counteracts the horizontal force of ship impact, cable tension and the vertical load of the superstructure, a bit like the tenon structure of ancient Chinese architecture.

According to the information from Hongyang port storage, on June 9, 2022, Lianyungang Hongyang port storage and Transportation Co., Ltd.

By checking the project site, listening to the reports and summaries of all units, and reviewing the project handover data, the representatives attending the meeting considered that the project met the handover and acceptance conditions and agreed to the handover and acceptance.

As the R & D and application of the first fully assembled high pile wharf in China, the π precast beam and slab has significantly improved the project quality and construction efficiency, and saved the construction period and cost.

Magnet Recess Former

The two berths are arranged continuously.

Hongyang port’s 64\65\liquid bulk cargo storage berth, together with the raw materials and finished products required by the new industrial development of the companies under Shenghong Petrochemical Group and the business development of the enterprises in Xuwei Petrochemical Park, will lay a solid foundation for the new journey of Lianyungang petrochemical industry.

As the first new fully assembled high piled wharf in China, the project includes one 80000 ton liquid bulk cargo berth (64\e berth, 100000 ton hydraulic structure) and one 100000 ton liquid bulk cargo berth (65\e berth).

The wharf surface is 588m long and 25m wide, including a 5-storey fire control building.

The project to be handed over for acceptance this time is the hydraulic building (structure) works of No.

The main cargo types are methanol, acrylonitrile and crude oil, with a design annual throughput of 6.6 million tons.

The most important stress-bearing structure of the high pile wharf is at the pile cap.

64~65 liquid bulk cargo berth, which is located in the six harbor basin in Xuwei port.