China Precast Magnet

Precast Concrete Accessories

Application of modular building composed of prefabricated foundation, prefabricated ground beam, and prefabricated concrete box structure in

Recently, Zhang Wei, Secretary of the Party Group and Director of the Beijing Municipal Commission of Planning and Natural Resources, led a team to investigate the post disaster recovery and reconstruction situation in Zhaitang Town, Mentougou District..

Zhang Wei highly praised the progress made in the relocation project of Yanhekou Village and fully affirmed the efforts made by Zhaitang Town and China Construction First Bureau for post disaster reconstruction. We need to strengthen daily supervision and inspection, strengthen the control of building indicators, especially in terms of geological disaster response capacity, main structure of houses, etc., and be cautious to ensure that a “satisfactory answer sheet” is handed over to the disaster stricken people in the western mountainous area of Beijing..

During the “23.7” catastrophic flood in the Haihe River basin, Yanhekou Village in Zhaitang Town, Mentougou District was severely affected. After the flood, China Construction First Engineering Bureau Design and Research Institute, China Construction First Engineering Bureau Construction and Development Company, Beijing China Construction Architectural Design Institute Co., Ltd., China Construction (Tianjin) Industrial Construction Engineering Co., Ltd., and China Construction Design and Research Institute Co., Ltd. were the first to invest in post disaster reconstruction work, jointly responsible for the design and construction of relocation projects. Recently, all prefabricated modular houses for the relocation project in Yanhekou Village, Mentougou, Beijing have been completed, and the “Fuchun Mountain Dwelling Map” in Mentougou has begun to take shape..

Beijing Mentougou Yanhekou Village Relocation Housing Project.

Earth excavation of 12000 cubic meters.

Installation of 891 prefabricated foundation components.

Installation of 1256 prefabricated ground beam components.

Installation of 654 prefabricated module rooms.

▲ Installation of prefabricated module room completed.

Adopting a combination of prefabricated foundation, prefabricated ground beam, and box structure.

Fully assembled structure from underground to above ground.

Fixing Socket

The model of full factory production and on-site installation of components.

Normal construction even in low winter temperatures.

Complete the main structure of 96 households in 30 days for the project.

All production and on-site installation work.

The project adopts architecture, structure, electromechanical, etc.

One click extraction software for 2D drawing BOM.

Required for future delivery and use.

Structural connection embedded parts, wire boxes and conduits, reserved holes, etc.

Complete all deepening of the component drawing process.

Efficiently completed nearly 3000 component drawings in 7 days.

China Construction Smart Factory Production Management System.

Implemented the prefabricated concrete components of the project.

Intelligent production scheduling, quality, and cost traceability throughout the entire process.

Ensure the achievement of production efficiency goals for prefabricated components in the project.

To ensure the construction progress of the project site.

Adopting a multi time collaborative production model within the factory.

Realize 100% demolding of all prefabricated components.

Source: China Construction First Engineering Group Construction and Development Co., Ltd.

Related Posts