Building a Station with “Building Blocks” – The First Floor of a Fully Precast and Assembled Station for Shenzhen Metro Line 22 Project is

On November 30th, at the construction site of the Liguang Station project on Shenzhen Metro Line 22, a 180T intelligent gantry crane lifted a precast floor component weighing 104.

Precast Round Ferrule

8 tons and accurately positioned it with the assistance of a rotating hook and a rotating balance beam.

With the successful completion of this critical operation, the fully precast and assembled station of Liguang Station officially entered a new stage of assembly construction.

.