Chongqing’s first precast underground comprehensive pipe gallery project will be completed and put into use by the end of the year

At the same time, as the municipal pipelines are laid underground, the urban skyline will be more open and bright after the construction of the underground pipe gallery.

Such design not only integrates and makes full use of underground space resources, reduces repeated construction and waste, but also facilitates the management and maintenance of pipelines.

It is planned to complete the whole line and put it into use by the end of this year.” According to Liu Hua, the project leader of Chongqing Yuxing Construction Investment Co., Ltd., the construction party, this is also the first precast underground comprehensive pipe gallery in the city, with an assembly rate of about 45%.

While saving 8 years of effort, it also shortens the construction period for nearly half a year…

The first assembled underground comprehensive pipe gallery in the city The underground comprehensive pipe gallery is a pipeline laying method for intensive laying and management of municipal pipelines, and is one of the symbols of modernization, science and technology, and intensification of urban construction.

Hualong.com – New Chongqing Client News (chief reporter Dong Jin) Recently, the reporter learned from the Municipal Commission of Housing and Urban Rural Development that the construction of the main structure of the underground comprehensive pipe gallery project in Banan District has been completed, and the whole line is planned to be completed and put into use by the end of 2022.

The greatest advantage of the underground comprehensive pipe gallery is to realize centralized management under the pipeline, avoid repeated excavation of the pavement due to the change of the pipeline route, and reduce the occurrence of “zipper roads”.

The underground comprehensive pipe gallery is designed with three cabins, the power and gas pipelines are independent cabins, and the communication and water supply pipelines are comprehensive cabins.

The underground comprehensive pipe gallery project in Banan District is located in Longzhouwan District B and Higher Vocational City.

“The project was officially started in 2019.

At present, the construction of the main structure has been completed, and equipment commissioning, ancillary works installation and other construction are under way.