The construction of production workshops has completed 60% of the total project and is expected to be completed in May next year.
Welcome to contribute: chstzcjzx@163.com 。.
Up to now, the main structure of the PC production workshop of the project has been completed, the office building, staff dormitory and canteen are under orderly construction, and the surrounding supporting facilities are promoted synchronously.
Recently, the relevant person in charge of Sanbing town led a team to the construction site to investigate the project progress and existing problems.
Text picture: Sanbing town / Editor: Zhou Huanhuan / proofreading: Chen Yan pays attention to the “forefront of investment promotion” to master the new trends of investment in Chaohu – sincerely invite people with lofty ideals around the world to pay attention to Chaohu, invest in Chaohu and help Chaohu.
Sinoma Baoye precast construction project has been actively promoted and steadily constructed since its commencement in October.
After the project is put into operation, the annual output of various precast building materials will be 125000 cubic meters.
It is expected that the annual income of the project will be 400million yuan after its completion, which can solve the employment of 300 local people.
Project introduction the construction project of the precast precast component production line of Anhui Sinoma Baoye construction industrialization Co., Ltd.
According to the person in charge of the site, the project faced many difficulties in the early stage, and finally started smoothly with the strong support of the municipal Party committee and the municipal government; At present, the project is advancing smoothly and orderly.
is planned to have a total investment of 310million yuan.