The precast modular building of CAS first appeared in Xiong’an New Area
The box is suitable for transportation, convenient for flexible combination, avoiding wet operation and reducing the seasonal restrictions of construction.
Scheme Design, Local Design and Research Center, Technical Standards, National Residential Engineering Consulting Co., Ltd., CIMC Modular Construction Investment Co., Ltd., Construction Drawing Design, Local Design and Research Center, National Residential Engineering Consulting Co., Ltd., BIM Design, BIM Design and Research Center, Interior Design, National Residential Engineering Consulting Co., Ltd., Environmental Art Research Institute, Production and Installation, CIMC Modular Construction Investment Co., Ltd., China Construction Integrated Housing Co., Ltd For more wonderful works and developments of China Construction Third Engineering Bureau Group Co., Ltd.
The box module was hoisted in place.
The design of office building and hotel is 4m × 12m × The 3.6m box-type module as the basic unit is spliced into a “cross” unit combination of about 1000-1200 square meters.
In the design of the box module in the Xiong’an Citizen Service Center-Enterprise Temporary Office Area, Academician Cui Kai and Liu Yanhui, the chief architect of the consultant, pushed forward the scientific research achievements, and integrated the concept of assembly technology into the design from the beginning of the project.
and CIMC Modular Construction Investment Co., Ltd.
The “cross” unit combination building is open to all sides, has good lighting and natural ventilation, and maximizes its integration into the natural environment.
Xiong’an Citizen Service Center-Enterprise Temporary Office Area Scheme Panorama Fully Assembled and Integrated Box Module Construction Technology In order to meet the requirements of rapid construction and respond to the national policy of promoting assembly, the enterprise temporary office area adopts the fully assembled and integrated box module construction technology developed by the Chinese Academy of Sciences and CIMC Modular Construction Investment Company, with the assembly rate of 80% – 90%.
The interior of the office box, the interior decoration and pipeline installation have been completed in one step.
The BIM Center of the Institute undertakes the BIM design task of the entire civil service center, including the area.
The unit layout and combination are flexible, and the growth is strong, which is suitable for changing according to the development needs.
On the morning of February 4, 2018, the first box module of the Xiong’an Citizen Service Center – the temporary office area of the enterprise was hoisted, marking the official landing of the modular building developed and designed by the Chinese Academy of Sciences in Xiong’an.
The design is designed to create an innovative, coordinated, green, open and shared office environment for the office staff of the enterprise, with strong innovation and demonstration, which will play a demonstration and promotion role in the construction of the Millennium City Xiong’an New Area.
Trapezoid Rubber Magnetic Chamfer
Since 2015, under the leadership of Master Ren Qingying, the Chinese Academy of Sciences and National Settlements Engineering Consulting Co., Ltd.
The modular and integrated construction system of container is composed of steel structure service core inside and box-type modular structure function body around.
The structure, interior decoration, exterior decoration, equipment and pipeline are all produced in the factory and transported to the construction site for unified hoisting, so as to minimize construction waste and achieve green construction.
Design renderings The rich courtyard space layout, rainwater garden ecological wetland, vertical green climbing vine planting and other designs in the general plan all reflect the green ecological architectural design concept.
The fully assembled and integrated box-module construction technology, which makes the structure, interior, exterior, equipment and pipeline all finished in the factory, is one of the explorations of the Chinese Academy in the field of assembly.
during the company’s on-site construction, welcome to pay attention to the WeChat ▼ of China Architectural Design Institute.
The local design center of the Institute, the National Habitat Engineering Consulting Co., Ltd., the Environmental Art Institute and other departments worked together to complete the entire design in just three months.
Among them, the total construction area of the temporary office area of enterprises is 36023 square meters, providing facilities such as office rooms, hotels, public services, etc., which are designed by China Architectural Design Institute Co., Ltd., with the chief architect Cui Kai as the design director, and the chief architect Liu Yanhui as the lead architect to organize and provide technical guidance.
Please press the QR code for a long time to pay attention.
.
The Xiong’an Citizen Service Center at the construction site is the first construction project of Xiong’an New Area, known as “the first bid of Xiong’an New Area”, and is the window of Xiong’an New Area to the whole country and even the world, including government services, planning and display, revolving housing, corporate office and other functions.
have jointly prepared the enterprise standard CIMC Technical Specification for Integrated Modular Building of Steel Structure, and the standard of China Association for Standardization of Engineering Construction, Technical Specification for Integrated Building of Box Steel Structure, which is prepared on this basis, is also about to be completed.
The interior decoration of the hotel can meet the use requirements after simple layout.
The innovative and exemplary temporary office space for design enterprises consists of six office buildings, one hotel and several commercial and service facilities.
Thanks to the fully assembled and integrated construction technology, the box module has realized factory production, and even the internal decoration is in place simultaneously.
After being transported to the construction site, it can be completed through simple installation.