Can tower crane foundations still be constructed in this way? Save time and money!
The second phase resettlement housing construction project in Xiema New Village, Chengnan Industrial Concentration Development Zone, Ziyang City, combined with its own project characteristics, adopts a labor-saving, time-saving, and land saving precast tower crane foundation to replace the traditional cast-in-place tower crane foundation, saving 35 days of construction period and 579800 yuan in costs.
.