How to achieve 10 days per floor for a nearly 2000 square meter precast structure with a height of 3.7 meters?

The main building of the hotel in the ZX-10CZ-04-36 plot hotel project in Jinghu New Area is a frame shear wall structure, with precast components of PC floor slabs.

Lifting Socket

Starting from the 4th floor, it is a standard floor with a floor height of 3.

7 meters.

The project achieved a breakthrough in the completion of a single floor of nearly 2000 square meters in 10 days through the collaborative construction of aluminum alloy formwork (referred to as “aluminum formwork”) and PC slabs.

.