Industrial Development Year | Yicheng Precast New Wall Material Production Project: Trial Production Launched in August of This Year
The main structure of the steel structure has entered the completion acceptance stage, and the construction of the roasting kiln and drying kiln has been completed.
The track outside the kiln is expected to be completed by the end of this month.
The next step will be the construction of the brick making system foundation and equipment installation.
Currently, we are making every effort to tackle the equipment installation challenge, and it is expected to be put into trial production in August this year, “said project manager Tang Maoqing.
.